Meeting opened in prayer by Pastor Bob.
- Carl reviewed with the Team his thoughts and preliminary drawings for the elevator, followed by Team discussion.
- Pat handed out his list of required church repairs. The Team discussed the desirability of considering the integration of HVAC/Mechanical project items into the multipurpose facility. (the remainder of the list will be discussed at next meeting)
- Richard handed out the Project Flow Chart, followed by Team discussion of timing and budget parameters.
- The Team received a folder of various drawings that Darrel Davis dropped off at the Church Office. Carl took the drawings for review. Also, the Team received an e-mail from "Studio/Gang/Architects" indicating that all First Presbyterian materials (sight survey, old blue prints and drawings of various proposals) would be Fed-Exed to the Church this week.
The above discussion led to the following action items:
- Prepare report to Session regarding HVAC - Pat
- Gather information regarding specifications and cost for Kone Elevators. - Carl
- Gather pre-engineered building literature and local contractor information. - Carl
- Update the Project Flow Chart (re: preliminary Zoning approval) and forward to Dale for Session review. - Richard
- Arrange appropriate file space in the Church for receiving and storing Church Blue Prints and Facility Materials. - Pastor Bob
- Bring Coffee to next meeting. - Dale
The Team agreed to next meet on Saturday, September 8, 2007 at 6:00 AM at the Church
No comments: