The Project Team has had three meetings (October 19, 23 and 28) at the Church. The purpose of these meetings has been to fulfill the Session's request for a project update to the Congregation to be given at the Congregational Meeting on November 2, 2008. The Session, at its October 13 meeting, asked the Project Team to see if a scaled down, revamped project can still be completed in line with the pledges received (total cash and pledges of $750,000). All three meetings were covered in Prayer by Pastor Bob, and proceeded as follows:
* The Team reviewed the three goals for the project as assigned by the Session when the Team was formed: elevator, repairs (Heating Ventilation and Air Conditioning - HVAC) and multi-purpose space.
* The budgeted amount for the elevator is $200,000 and for the Mechanical/Electrical/Plumbing (MEP including HVAC) is $300,000. While the final cost of the Elevator and MEP may vary some based on the final project scope, these are relatively fixed costs; and the Team agreed that a total budget of $500,000 should be maintained for these items. Therefore, the rest of the project should be resized accordingly.
* The Team discussed the need to plan for future growth given the reduced space in the revised Phase I plan. Additional space (and expense) could be added to future phases of the project.
As a result of these meetings the following action items were assigned:
1) Work with the architect on revised space requirements - Dale
2) Discuss cost of revised project with area contractors to determine cost savings - Carl
3) Prepare a presentation for the Congregational Meeting - Richard
The next Project Team Meeting will be scheduled following Feedback from the Congregational Meeting and as additional project information is made available.
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment